The Mallinckrodt Senior Residence is a rehab development of a former college in Wilmette, Illinois. The plans for the development included the addition of underground parking for residents, staff and visitors.
Although the DeckFast system is usually used for creating a flat slab, it can accommodate some sloped conditions. This project featured a slight drainage slope on the base slab and an East-to-West slope on the slab being supported. The 9" and 10½" slab was elevated at 10'-6¾" and also had 10' x 10' drop heads which were supported by FrameFast™ shoring with aluminum joists and stringers. Plans called for approximately 30,000 ft2 of DeckFast deck panels and drop heads.
DeckFast is a system that consists of Post Shores, 5.9' x 5.9' aluminum panels and smaller fillers with a 10mm plywood face. Working around the drop heads, the contractor used as many large DeckFast panels as possible and then pieced in the smaller areas. By adjusting the elevation of the post shores with the threaded collar, the contractor was able to create the drainage slope.
Advantages of the system include:
  • An average of 1000 ft2 per worker per day on a flat slab.
  • Light-weight frames make moving and placing panels easier.
  • Assembly from below provides workers with a stable work surface.
  • Tripods provide stability in the initial setting operations.
  • 2-prong and 4-prong support bearings for the panels.
  • A quick-release pin allows easy stripping with a hammer blow.

DeckFast™ Shoring System

VIEW SYSTEM
While most of our site features are available using your current browser, some new features we think you’ll like, require a quick browser update to perform properly. Please consider downloading one of the browsers from the recommendations below. Doing so will provide you with the best user experience as you explore www.daytonsuperior.com.