The Colton Cement Company was expanding their plant by adding new silos. These tall structures are very heavy, and require a 6' thick concrete pad with a dense rebar cage to support them.
Generation Concrete Construction, the General Contractor for the project, was looking for a forming system that would allow them to set up quickly to minimize disruption for the rebar crew. Symons suggested the Rapid Clamp system ganged in a horizontal orientation. The clamp attachments make it a fast system to configure, and all the equipment is rentable, which suited their short-term need perfectly
Because the contractor had never used the system before, Symons provided field assistance. The forming crew adapted to the gang procedures, and quickly completed the project.

Rapid Clamp™ Forming System

VIEW SYSTEM
While most of our site features are available using your current browser, some new features we think you’ll like, require a quick browser update to perform properly. Please consider downloading one of the browsers from the recommendations below. Doing so will provide you with the best user experience as you explore www.daytonsuperior.com.

Microsoft Edge
Google Chrome
Mozilla Firefox